Ethiopian Electric Power placed overall completion of the Koysha hydropower project at 78.36% in its first-quarter performance review, Fana Media reported on November 13. The state utility had reported that work passed 77% in late August.

Fana reported that crews placed about 250,000 cubic meters of roller-compacted concrete during the quarter, against a target of 255,000 cubic meters. The utility also reported continuing work on equipment for six generating units.

Koysha is under construction on the Omo River. The figures measure construction progress, and turbine testing remains a future step in the utility’s project schedule.

Sources & references

  1. Fana Media’s November 13 report on the utility’s quarterly review
  2. Ethiopian Electric Power’s August construction update
Share by email

Editorial information provides context and is not individualized financial, investment, mortgage or legal advice. Consider dates, source limitations and your circumstances.